Hydroelectric Plant Pedregalito 1
Company Name: Generadora Pedregalito, S.A.
Technical Data
Installed Capacity: | 20MW |
Generation: | 85 GWh/year based on average historical hydrology |
Equipment: | Two groups of Andritz turbogenerators 10MW capacity each |
Design flow: | 40m³/s |
Interconnection:: | 7 km 34.5 kV line connected to ETESA’s Boquerón 3 substation |
Pedregalito 1, which finalized construction in April 2011, is located in Boquerón District, Province of Chiriquí, approximately 20 kilometers west of the city of David.